Leonard Johnson
36%
49
Construction Permits
55 total
33
Currently Open
42
Rate-Eligible
permits > 1yr old
2014–2025
Years Active
Closure rate based on permits older than 1 year. “Issued” and “Stop Work” statuses are excluded.
Performance by Permit Type
Building42 rated
35.7% closed vs 30% median, 5.8 points higher
Median based on all applicants with 20+ rated permits in each category. Only permits older than 1 year are rated.
Year-by-Year Summary
2025
—
Open6
Closed1
Too early to rate — permits need 1 year to mature
2024
15.4%
Open11
Closed2
2 closed / 13 rated
2023
40.0%
Open6
Closed4
4 closed / 10 rated
2022
66.7%
Open4
Closed8
8 closed / 12 rated
2021
0.0%
Open2
Closed0
0 closed / 2 rated
2014
20.0%
Open4
Closed1
1 closed / 5 rated
All Permits
55 permits
| Status | Permit # | Address | Issued▼ | |||
|---|---|---|---|---|---|---|
| Open | ALT1735526 | Long Form/Alteration Permit | 360 Huntington AV, Boston | Sep 23, 2025<1yr | Mar 23, 2026 | $10,000 |
| Open | A1736146 | Amendment to a Long Form | 70 Forsyth ST, Boston | Jun 25, 2025<1yr | Dec 25, 2025 | $0 |
| Open | ALT1683331 | Long Form/Alteration Permit | 360 Huntington AV, Boston | May 2, 2025<1yr | Nov 2, 2025 | $833,847 |
| Open | ALT1673879 | Long Form/Alteration Permit | 70 Forsyth ST, Boston | May 1, 2025<1yr | Nov 1, 2025 | $1,597,983 |
| Closed | ALT1701866 | Long Form/Alteration Permit | 1155-1175 Tremont ST, Boston | Apr 25, 2025<1yr | Oct 25, 2025 | $564,806 |
| Open | ALT1696034 | Long Form/Alteration Permit | 337-339 Huntington AV, Boston | Apr 15, 2025<1yr | Oct 15, 2025 | $743,212 |
| Open | SF1701051 | Short Form Bldg Permit | 360 Huntington AV, Boston | Mar 31, 2025<1yr | Sep 30, 2025 | $964,518 |
| Open | SF1673898 | Short Form Bldg Permit | 17-23 Forsyth ST, Boston | Dec 2, 2024 | Jun 2, 2025 | $300,000 |
| Open | SF1673898 | Short Form Bldg Permit | 17-23 Forsyth ST, Boston | Dec 2, 2024 | Jun 2, 2025 | $300,000 |
| Closed | COO1668006 | Certificate of Occupancy | 110 Forsyth ST, Boston | Nov 8, 2024 | — | $593,252 |
| Closed | ALT1611992 | Long Form/Alteration Permit | 400 Huntington AV, Boston | Oct 24, 2024 | Apr 24, 2025 | $31,130 |
| Closed | ALT1599144 | Long Form/Alteration Permit | 110 Forsyth ST, Boston | Jul 25, 2024 | Jan 25, 2025 | $869,718 |
| Open | SF1611993 | Short Form Bldg Permit | 360 Huntington AV, Boston | Jul 22, 2024 | Jan 22, 2025 | $224,471 |
| Closed | COO1615385 | Certificate of Occupancy | 110 Forsyth ST, Boston | Jun 27, 2024 | — | $1,489,740 |
| Open | ALT1591740 | Long Form/Alteration Permit | 110 Forsyth ST, Boston | Jun 11, 2024 | Dec 11, 2024 | $593,252 |
| Open | SF1600665 | Short Form Bldg Permit | 110 Forsyth ST, Boston | May 28, 2024 | Nov 28, 2024 | $106,554 |
| Open | SF1595636 | Short Form Bldg Permit | 110 Forsyth ST, Boston | May 28, 2024 | Nov 28, 2024 | $278,825 |
| Open | SF1591762 | Short Form Bldg Permit | 50 Leon ST, Boston | May 3, 2024 | Nov 3, 2024 | $779,860 |
| Open | SF1595870 | Short Form Bldg Permit | 440 Huntington AV, Boston | May 3, 2024 | Nov 3, 2024 | $4,857,539 |
| Open | SF1591745 | Short Form Bldg Permit | 110 Forsyth ST, Boston | May 2, 2024 | Nov 2, 2024 | $42,850 |
| Open | SF1577608 | Short Form Bldg Permit | 110 Forsyth ST, Boston | Mar 21, 2024 | Sep 21, 2024 | $184,340 |
| Open | ALT1544008 | Long Form/Alteration Permit | 110 Forsyth ST, Boston | Jan 29, 2024 | Jul 29, 2024 | $1,489,740 |
| Open | SF1539722 | Short Form Bldg Permit | 110 Forsyth ST, Boston | Oct 31, 2023 | Apr 30, 2024 | $28,200 |
| Closed | ALT1520767 | Long Form/Alteration Permit | 400 Huntington AV, Boston | Oct 18, 2023 | Apr 18, 2024 | $155,000 |
| Closed | COO1533306 | Certificate of Occupancy | 70 Forsyth ST, Boston | Oct 12, 2023 | — | $1,430,203 |
| Open | SF1517054 | Short Form Bldg Permit | 400 Huntington AV, Boston | Aug 31, 2023 | Feb 29, 2024 | $125,000 |
| Closed | SF1472188 | Short Form Bldg Permit | 106-122 Saint Stephen ST, Boston | May 24, 2023 | Nov 24, 2023 | $320,335 |
| Open | SF1461677 | Short Form Bldg Permit | 50 Leon ST, Boston | May 9, 2023 | Nov 9, 2023 | $1,934,130 |
| Closed | ALT1455040 | Long Form/Alteration Permit | 70 Forsyth ST, Boston | May 3, 2023 | Nov 3, 2023 | $1,430,203 |
| Closed | ALT1444885 | Long Form/Alteration Permit | 110 Forsyth ST, Boston | May 2, 2023 | Nov 2, 2023 | $655,271 |
| Open | SF1455026 | Short Form Bldg Permit | 70 Forsyth ST, Boston | Apr 27, 2023 | Oct 27, 2023 | $0 |
| Open | SF1463847 | Short Form Bldg Permit | 359-369 Huntington AV, Boston | Apr 24, 2023 | Oct 24, 2023 | $587,200 |
| Open | ALT1419939 | Long Form/Alteration Permit | 1155-1175 Tremont ST, Boston | Feb 23, 2023 | Aug 22, 2023 | $7,560 |
| Open | SF1408115 | Short Form Bldg Permit | 179-181 Camden ST, Roxbury | Nov 8, 2022 | May 8, 2023 | $480,749 |
| Open | SF1398303 | Short Form Bldg Permit | 30 Leon ST, Boston | Oct 20, 2022 | Apr 20, 2023 | $33,800 |
| Closed | SF1363536 | Short Form Bldg Permit | 400 Huntington AV, Boston | Oct 4, 2022 | Apr 4, 2023 | $102,924 |
| Open | SF1348751 | Short Form Bldg Permit | 1155-1175 Tremont ST, Boston | Jul 21, 2022 | Jan 21, 2023 | $1,245,787 |
| Closed | SF1332081 | Short Form Bldg Permit | 10 Speare PL, Boston | Jul 13, 2022 | Jan 13, 2023 | $279,810 |
| Closed | SF1337909 | Short Form Bldg Permit | 106-122 Saint Stephen ST, Boston | Jul 1, 2022 | Jan 1, 2023 | $779,961 |
| Closed | SF1344237 | Short Form Bldg Permit | 11 Leon ST, Boston | Jun 29, 2022 | Dec 29, 2022 | $617,658 |
| Closed | SF1332089 | Short Form Bldg Permit | 70 Forsyth ST, Boston | Jun 14, 2022 | Dec 14, 2022 | $891,135 |
| Closed | SF1332083 | Short Form Bldg Permit | 50 Leon ST, Boston | Jun 14, 2022 | Dec 14, 2022 | $2,778,940 |
| Closed | ALT1277327 | Long Form/Alteration Permit | 32 Fruit ST, Boston | Apr 21, 2022 | Oct 21, 2022 | $469,000 |
| Closed | ALT1277327 | Long Form/Alteration Permit | 32 Fruit ST, Boston | Apr 21, 2022 | Oct 21, 2022 | $469,000 |
| Open | ALT1272840 | Long Form/Alteration Permit | 73 High ST, Charlestown | Jan 5, 2022 | Jul 5, 2022 | $537,000 |
| Open | SF1201881 | Short Form Bldg Permit | 10 Speare PL, Boston | Jun 17, 2021 | Dec 17, 2021 | $1,196,468 |
| Open | SF1192932 | Short Form Bldg Permit | 10 Speare PL, Boston | Jun 2, 2021 | Dec 2, 2021 | $50,000 |
| Closed | COO380106 | Certificate of Occupancy | 28 State ST, Boston | Sep 24, 2014 | — | $358,416 |
| Closed | COO364656 | Certificate of Occupancy | 20-30 Channel Center ST, Boston | Jul 11, 2014 | — | $347,655 |
| Closed | COO365036 | Certificate of Occupancy | 20-30 Channel Center ST, Boston | May 22, 2014 | — | $347,655 |
Page 1 of 2